• Blockwork and core fill completed to level 2.
• Formwork has started to level 2.
• Plumbers have completed works in basement to stacks and continue to rise through the building.
• Electricians continue works in basement level.
• Mech Vent continues in basement level.
• Slab pour for level 2 booked mid to late this month.
Building 1 – (lots 1 – 4)
• The Joinery fit out completed.
• Internal painting nearing completion .
• Internal tiling 90% complete.
•Stone benchtops install has commenced.
Building 2 – (lots 5 – 8)
• Gyprock installation nearing completion.
• Joinery install has started.
• Carpentry fix out completed.
• Internal painting continues.
Building 3 – (Lots 9 – 13)
• Gyprock installation to begin this week .
• Electrical and Plumbing rough in completed.
• Cladding to begin this week (9/10).
Building 4 – (Lots 14 – 17)
• All roofs completed.
• Frame tie down completed
• Window install to begin mid-October
• Building Wrap to start mid this month with cladding to begin by the end of the month.