Find out the latest updates from the Development team below.

Blockwork and core fill completed to level 2.

Formwork has started to level 2.

• Plumbers have completed works in basement to stacks and continue to rise through the building.

Electricians continue works in basement level.

Mech Vent continues in basement level.

Slab pour for level 2 booked mid to late this month.

                                                  

Find out the latest updates from the Development team below.

 

Building 1 – (lots 1 – 4)

• The Joinery fit out completed.

• Internal painting nearing completion .

• Internal tiling 90% complete.

•Stone benchtops install has commenced.

 

Building 2 – (lots 5 – 8)

• Gyprock installation nearing completion.

• Joinery install has started.

• Carpentry fix out completed.

• Internal painting continues.

 

Building 3 – (Lots 9 – 13)

• Gyprock installation to begin this week .

• Electrical and Plumbing rough in completed.

• Cladding to begin this week (9/10).

 

Building 4 – (Lots 14 – 17)

All roofs completed.

• Frame tie down completed

• Window install to begin mid-October

• Building Wrap to start mid this month with cladding to begin by the end of the month.