• Basement walls and columns are complete.
• Basement slab works are complete.
• The podium slab works have commenced (pictured).
Two pumps were operating most of the day with two trucks loading each pump simultaneously. Approx. 80 trucks in total with a truck arriving every 6 minutes or so. More than 20 concreters installing about 550m3 of concrete in total.