Find out the latest updates from the Development team below.

• Basement works continue with all excavation works complete.

• Under slab drainage works to the basement are complete.

• The pouring of pad and strip footings and has commenced with approximately half of the pad footings poured.

• Columns and external walls are due to commence this month.

 


Find out the latest updates from the Development team below.

The installation of the lift is complete.

External works have commenced.

Cleaners have commenced on all levels internally.

Externally, tiling, fencing and balustrade works continue.

Commissioning of air conditioners to units and mechanical exhausts to carpark has commenced.

External works to the rubbish collection area have also commenced.

Register your interest for upcoming releases by contacting our sales team on 1800 461 860.