• Basement works continue with all excavation works complete.
• Under slab drainage works to the basement are complete.
• The pouring of pad and strip footings and has commenced with approximately half of the pad footings poured.
• Columns and external walls are due to commence this month.
• The installation of the lift is complete.
• External works have commenced.
• Cleaners have commenced on all levels internally.
• Externally, tiling, fencing and balustrade works continue.
• Commissioning of air conditioners to units and mechanical exhausts to carpark has commenced.
• External works to the rubbish collection area have also commenced.