The Poolside Terrace Homes are progressing! Check out below the latest updates.
Brickworks has commenced to all slabs, and is approximately 80% complete
Timber framing has commenced to 2 of the 4 concrete slabs, and is approximately 30% complete
Window and sliding door framing have been delivered to site for install as the carpenters progress
Plumbing and electrical rough ins are forecast to commence next month
Lilly Apartments Construction Update
Lilly Apartments construction is progressing! Find out the latest updates from the construction team below.
External rendering, finishes, and painting has been completed to level 4, with trades working from the top down
Render and paint to shared spaces is now 80% complete, with tiling now commenced to level 4.
Ground floor internal tiling is complete, Cabinetry is complete, all benchtops have been installed, whitegoods install is at 50%, and installation of plumbing fittings (toilets, sinks, taps) has commenced.
Level 1 internal tiling is 90% complete, cabinetry is 90% complete, all benchtops have been installed, whitegoods install has commenced, and installation of plumbing fittings has commenced.
Level 2 cabinetry is 90% complete, internal tiling is 70% complete, and all benchtops have been installed.
Level 3 internal and external wet areas have been prepped for tiling, cabinetry is 80% complete, install of internal doors has commenced.
Level 4 balcony tiling works has commenced, 60% of wall sheeting has been installed with 10% flushed and sanded.
Register your interest for upcoming releases by contacting our sales team on 1800 461 860.