Find out the latest updates from the Development team below.

• Basement works continue with all excavation works complete.

• Under slab drainage works to the basement are complete.

• The pouring of pad and strip footings and has commenced with approximately half of the pad footings poured.

• Columns and external walls are due to commence this month.

 


Find out the latest updates from the Development team below.

• The installation of the lift is complete.

• External works have commenced.

• Cleaners have commenced on all levels internally.

• Externally, tiling, fencing and balustrade works continue.

• Commissioning of air conditioners to units and mechanical exhausts to carpark has commenced.

• External works to the rubbish collection area have also commenced.